[LSC-PREP] Ecliptic/Roccor Team Meeting Notes & Proposal Update

Michael Fitzgerald Michael.B.Fitzgerald at asu.edu
Fri Nov 2 11:52:48 MST 2018


Hi All - here are the action items and notes out of our (very productive) meeting with Ecliptic and Roccor yesterday.

To all team members - please make sure your NSPIRES profile is established and current by COB 11/07/18. Instructions are here: https://nspires.nasaprs.com/external/aboutRegistration.do;jsessionid=pU7VvxuVf5okeUzEVGGDFC0KgQajeKe1XsIsri-Gunh4kDr1R5nY!-27841465!cassini3.nasaprs.com!7006!9008!36618162!cassini2.nasaprs.com!7006!9007

Please note your organization needs to approve your registration if not already signed up. You MUST be listed in the Step-1 proposal if you are to be included in Step-2.

I'm still combing through all the relevant documentation and am working on a proposal checklist with requirements and roles and responsibilities. I hope to have that out to the team by early next week. Have a great weekend!

11/01/18 Ecliptic Concept Meeting

Action Items
*         Self-register in NSPRIRES (All)
o    Due by 11/07/18
*         Review Astrobotic lander capabilities - Mark
*         Add science goal? - Mark
o    Image the deck to determine how much dust is collected on the lander
*         Review Lander RFP for technical details - Michael
*         Prepare proposal checklist, requirements document, and assignments - Michael
*         Prepare reference document and secured, collaboration file repository - Michael
*         Draft Step-1 4000 character project summary - Mark/Rex
o    First draft due for circulation EOD 11/06/18
o    Submit by 11/09/18 (goal)
*         Continue technical discussions with Roccor - Rex/Mike
*         Schedule recurring team meeting - Michael

Roccor Info
*         Boom
o    Length
*         Minimum of 21 inches
*         Longer if possible
*         Ideally 24-36in
*         Roccor - Thermal leads, rollable booms expert (Bruce bruce.davis at roccor.com) (Will Francis, VP)
o    Longmont, CO
o    Founded 2011; 40 people
o    Business is deployable structures
*         Booms
*         Antennas
*         Solar Arrays
*         Instrument booms
o    Flight spares or other flight qualified hardware?
o    Lead times?
o    Gimbaling has low to no heritage
o    Deployable and retractable boom
o    Boom height
*         More is better
o    Harnessing
*         Data lines down the boom has low TRL
*         Spooling is a concern
o    Boom is 1in in diameter
o    Cost: $100-200k?
*         Perhaps lower, but need additional information on this.

Ecliptic
*         Camera
o    FOV
*         15-30 degrees
*         Focus 12in out to infinity
o    Camera head ~2kg fully loaded

General
*         Questions:
o    Propose proposal review board be project SRB?
*         Vacation for Rex
o    Nov 26 - December 17
*         Ecliptic will need FFP subcontract
*         Descope/Baseline/Threshold
o    Remove descent imaging.
o    Demonstrate the instrument could last a lunar day
*         NASA Requirements
o    Tailored Class D.
*         Color imaging an open issue
*         Logo partners?


Michael Fitzgerald<https://webapp4.asu.edu/directory/person/857728> | Project Coordinator, Research PMO
Arizona State University | Office for Knowledge Enterprise Development | Operations
t 480-965-1968 | f 480-965-2455
michael.b.fitzgerald at asu.edu<mailto:michael.b.fitzgerald at asu.edu> |  http://researchadmin.asu.edu<http://researchadmin.asu.edu/>
How am I doing? Please email my supervisor<mailto:kevin.reinhart at asu.edu>.

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.ser.asu.edu/pipermail/lsc-prep/attachments/20181102/8420b020/attachment-0001.html>


More information about the LSC-PREP mailing list