[LSC-PREP] Ecliptic/Roccor Team Meeting Notes & Proposal Update
Michael Fitzgerald
Michael.B.Fitzgerald at asu.edu
Fri Nov 2 11:52:48 MST 2018
Hi All - here are the action items and notes out of our (very productive) meeting with Ecliptic and Roccor yesterday.
To all team members - please make sure your NSPIRES profile is established and current by COB 11/07/18. Instructions are here: https://nspires.nasaprs.com/external/aboutRegistration.do;jsessionid=pU7VvxuVf5okeUzEVGGDFC0KgQajeKe1XsIsri-Gunh4kDr1R5nY!-27841465!cassini3.nasaprs.com!7006!9008!36618162!cassini2.nasaprs.com!7006!9007
Please note your organization needs to approve your registration if not already signed up. You MUST be listed in the Step-1 proposal if you are to be included in Step-2.
I'm still combing through all the relevant documentation and am working on a proposal checklist with requirements and roles and responsibilities. I hope to have that out to the team by early next week. Have a great weekend!
11/01/18 Ecliptic Concept Meeting
Action Items
* Self-register in NSPRIRES (All)
o Due by 11/07/18
* Review Astrobotic lander capabilities - Mark
* Add science goal? - Mark
o Image the deck to determine how much dust is collected on the lander
* Review Lander RFP for technical details - Michael
* Prepare proposal checklist, requirements document, and assignments - Michael
* Prepare reference document and secured, collaboration file repository - Michael
* Draft Step-1 4000 character project summary - Mark/Rex
o First draft due for circulation EOD 11/06/18
o Submit by 11/09/18 (goal)
* Continue technical discussions with Roccor - Rex/Mike
* Schedule recurring team meeting - Michael
Roccor Info
* Boom
o Length
* Minimum of 21 inches
* Longer if possible
* Ideally 24-36in
* Roccor - Thermal leads, rollable booms expert (Bruce bruce.davis at roccor.com) (Will Francis, VP)
o Longmont, CO
o Founded 2011; 40 people
o Business is deployable structures
* Booms
* Antennas
* Solar Arrays
* Instrument booms
o Flight spares or other flight qualified hardware?
o Lead times?
o Gimbaling has low to no heritage
o Deployable and retractable boom
o Boom height
* More is better
o Harnessing
* Data lines down the boom has low TRL
* Spooling is a concern
o Boom is 1in in diameter
o Cost: $100-200k?
* Perhaps lower, but need additional information on this.
Ecliptic
* Camera
o FOV
* 15-30 degrees
* Focus 12in out to infinity
o Camera head ~2kg fully loaded
General
* Questions:
o Propose proposal review board be project SRB?
* Vacation for Rex
o Nov 26 - December 17
* Ecliptic will need FFP subcontract
* Descope/Baseline/Threshold
o Remove descent imaging.
o Demonstrate the instrument could last a lunar day
* NASA Requirements
o Tailored Class D.
* Color imaging an open issue
* Logo partners?
Michael Fitzgerald<https://webapp4.asu.edu/directory/person/857728> | Project Coordinator, Research PMO
Arizona State University | Office for Knowledge Enterprise Development | Operations
t 480-965-1968 | f 480-965-2455
michael.b.fitzgerald at asu.edu<mailto:michael.b.fitzgerald at asu.edu> | http://researchadmin.asu.edu<http://researchadmin.asu.edu/>
How am I doing? Please email my supervisor<mailto:kevin.reinhart at asu.edu>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.ser.asu.edu/pipermail/lsc-prep/attachments/20181102/8420b020/attachment-0001.html>
More information about the LSC-PREP
mailing list